Project Procurement Management – PMBOK 5.0 | Lecturio von Whizlabs Software

video locked

Über den Vortrag

Der Vortrag „Project Procurement Management – PMBOK 5.0 | Lecturio“ von Whizlabs Software ist Bestandteil des Kurses „Project Management Professional - Training“. Der Vortrag ist dabei in folgende Kapitel unterteilt:

  • Introduction
  • Plan Procurement Management
  • Contract types
  • Conduct Procurement
  • Control Procurement
  • Close Procurements

Quiz zum Vortrag

  1. Conduct Procurements
  2. Plan Procurement Management
  3. Control Procurements
  4. Close Procurements
  1. Cost Reimbursable
  2. Fixed Price
  3. Time & Material
  4. Purchase order
  1. Fixed Price
  2. Cost Reimbursable
  3. Time & Material
  4. Purchase order
  1. Time & Material
  2. Cost Reimbursable
  3. Fixed Price
  4. Purchase order
  1. FFP
  2. CPAF
  3. CPIF
  4. Time and Material
  1. CPAF
  2. FFP
  3. CPIF
  4. Time and Material
  1. Availability of suitable vendors in the market
  2. Existing Project Management Information Systems
  3. Cost to Quality
  4. Efforts needed to integrate Suppliers’ products with your product.
  1. Transfer
  2. Mitigate
  3. Accept
  4. Avoid
  1. Switch to a FP contract whenever possible.
  2. Apply stringent audit process for completed deliverable.
  3. Scrutinize the bills raised by the contractor.
  4. Switch to a CPIF contract and motivate the contractor to cut cost.
  1. Review the termination clause in the contract.
  2. Perform Contract/Administrative closure
  3. Refer to the SOW for payment clauses.
  4. Perform Contract negotiations
  1. EAC
  2. SPI
  3. Milestones achieved.
  4. SV
  1. Administrative closure pending
  2. Incomplete
  3. Complete
  4. Null & Void
  1. Synchronization of objectives
  2. Better quality of the product/services
  3. Schedule compression
  4. Cost saving
  1. Protect the relationship with the seller.
  2. Synchronization of objectives
  3. Obtain a fair price.
  4. Obtain maximum benefits out of the vendor.
  1. Plan Procurement Management
  2. Conduct Procurements
  3. Control Procurements
  4. Close Procurements
  1. Cost Reimbursable
  2. Fixed Price
  3. Time & Material
  4. Purchase order
  1. lease the item
  2. buy the item
  3. Can’t be determined
  4. The lease cost is same as purchase cost
  1. The contract SOW
  2. The Procurement management plan
  3. The project scope statement
  4. The Scope management plan
  1. Unknown till the end of the project
  2. Proportional to the number of days spent
  3. A fixed value as defined in the contract
  4. Always lower than the CPFF projects
  1. Proportional to the number of days spent
  2. Unknown till the end of the project
  3. A fixed value as defined in the contract
  4. Always lower than the CPFF projects

Dozent des Vortrages Project Procurement Management – PMBOK 5.0 | Lecturio

 Whizlabs Software

Whizlabs Software

Whizlabs provides end to end certification preparation solutions for Oracle Java and Project Management Certification. The e-learning company places value on high-class video and audio quality to ensure a user-friendly learning experience.

Kundenrezensionen

(1)
5,0 von 5 Sternen
5 Sterne
5
4 Sterne
0
3 Sterne
0
2 Sterne
0
1  Stern
0


Auszüge aus dem Begleitmaterial

... - Must be involved in the creation of contracts. - Identify risks and incorporate mitigation and allocation of risks into the contract. - Fit the schedule for completion of the procurement process into the schedule for the project. - Be involved during contract negotiation. - Protect the integrity of the project to get the work done. - Protect the relationship with the seller. ...

.. A contract typically includes: - SOW - Schedule/period of performance - Roles and responsibilities - Pricing and payment criteria - Acceptance criteria - Warranty and product support clauses - Limitation of liability - Fees, penalty, incentive related clauses - Change request handling procedures - Payment procedures - Termination and dispute handling mechanism - The buyers must select the appropriate type of contract for what they are buying. Contract types: There are three different contract types to choose from, depending on the nature of the project being outsourced. - cost reimbursable contract - CPFF (cost plus fixed fee) - CPPC (cost plus percentage cost) - CPIF (cost plus incentive fee) ...

... If the project is completed sooner, the seller will receive an additional amount, say $10,000. CPAF (Cost plus award fee): Buyer will pay all costs plus an apportionment of bonus based on performance (similar to CPIF). Fixed price contract: In this type of a contract, one fixed price is agreed for all the work. Buyer has least cost risk and risk of cost going higher is borne by the seller. This type is most appropriate if buyer can describe complete scope of work. ...

... - States if independent estimates will be used during proposal evaluation. Also includes: - The reporting requirements vis-à-vis procurement department ...

... When proposals from multiple vendors are received, evaluation criteria are applied to select the most suitable vendor of the lot. Evaluation criteria are used to score the proposals and may be subjective or objective in nature. It can be limited to price if the procurement item is readily available. ...

... - Watch for seller charges that were not part of the original plan. - Re-estimate the cost of the project. Time & Material Contract: - Provide day-to-day direction to the seller. - Attempt to get concrete deliverables. - Make sure the number of hours spent on work is reasonable. - Watch for situations when switching to a different form of contract makes sense. ...

... Contract closure is done when a contract ends or when a contract is terminated before the work is completed. There are two types of the closure procedures. ..