Project Cost Management by Grey Campus

video locked

About the Lecture

The lecture Project Cost Management by Grey Campus is from the course Project Management Professional. It contains the following chapters:

  • Section Overview and Objectives
  • Plan Cost Management
  • Estimate Cost
  • Determine Budget
  • Earned Value Management
  • Forecasting

Included Quiz Questions

  1. Cost
  2. Money
  3. Liability
  4. Trade
  1. To complete a project within an approved budget.
  2. To complete a project for as little cost as possible.
  3. To provide truthful and accurate cost information on projects.
  4. To ensure that an organization's money is used wisely.
  1. A cost baseline
  2. Activity cost estimates
  3. Basis of estimates
  4. Project documents updates
  1. -5%
  2. 5%
  3. - $5
  4. $5
  1. Management
  2. Contingency
  3. Financial
  4. Baseline
  1. Parametric
  2. Analogous
  3. Bottom-up
  4. Top-down
  1. Project cost budgeting
  2. Reserve analysis
  3. Life Cycle costing
  4. Earned value analysis
  1. Earned value management
  2. Reserve analysis
  3. Life Cycle costing
  4. Project cost budgeting
  1. The cost variance is $500, which is under budget.
  2. The cost variance is -$500, which is over budget.
  3. The cot variance is -$500, which is under budget.
  4. The cost variance is $500, which is over budget.
  1. It is ahead of schedule and over budget.
  2. It is ahead of schedule and under budget.
  3. It is behind schedule and under budget.
  4. It is behind schedule and over budget.
  1. Bottom-up
  2. Analogous
  3. Parametric
  4. Critical Path
  1. Parametric
  2. Analogous
  3. Critical Path
  4. Bottom-up
  1. Analogous
  2. Parametric
  3. Bottom-up
  4. Critical Path
  1. order of magnitude.
  2. definitive.
  3. conceptual.
  4. preliminary.
  1. fixed cost.
  2. direct cost.
  3. indirect cost.
  4. variable cost.
  1. opportunity cost.
  2. direct cost.
  3. fixed cost.
  4. benefit cost ratio.
  1. you are getting less than you planned for each dollar spent.
  2. you are ahead of schedule.
  3. you are behind schedule.
  4. you are getting more than you planned for each dollar spent.
  1. Those that involve the actual production of the product
  2. Those that are fixed
  3. Those that are variable
  4. Those that can be estimated accurately
  1. 0,82
  2. 1,2
  3. -1000
  4. 500
  1. 0,9
  2. 1,1
  3. 1000
  4. -500
  1. How much, total, the project will cost
  2. How much more money it will take to finish
  3. How much has been spent to date
  4. The same as BAC-PV
  1. a sophisticated project justification method.
  2. an estimating method.
  3. a basic project justification method.
  4. part of earned value analysis.
  1. none of the answers.
  2. you are ahead of schedule and overspent.
  3. you are behind schedule and overspent.
  4. ou are ahead of schedule and overspent

Author of lecture Project Cost Management

 Grey Campus

Grey Campus


Customer reviews

(1)
5,0 of 5 stars
5 Stars
5
4 Stars
0
3 Stars
0
2 Stars
0
1  Star
0


Excerpts from the accompanying material

... What is cost management? What are the processes of cost management? What is the cost management plan and what does it establish? The different ways of estimating costs of ...

... the project can be completed within the approved budget. Processes include: Plan ...

... cost of the resources needed to complete project activities. Key benefit: Provides guidance and direction on how the ...

... Level of Accuracy (e.g + or - 10%). Organizational procedure links. Control thresholds (% deviations from the baseline ...

... Key benefit: Determines the amount of cost required to complete project work, inputs tools & techniques outputs. 1. Cost management plan. 2. Human resource management plan. 3. Scope baseline ...

... & TechniquesOutputs.1. Cost management plan. 2. Scope baseline. 3. Activity cost estimates. 4. Basis of estimates. 5. Project schedule. 6.Resource calendars. 7. Risk register. 8. Agreements. 9. Organizational process assets. 1. Cost aggregation ...

... changes to the cost baseline. Key benefit: Provides a means to recognize variance from the plan in order to take corrective action an minimize risk. Inputs tools ...

... monitors 3 key dimensions for each work package and control account: 1. Planned ...

... also be monitored: Schedule variance (SV) - ahead of behind delivery date SV = EV - PV. Cost variance (CV) - over or under budget ...

... EAC forecast for ETC work considering both SPI and CPI ...

... is required to be achieved with the remaining resources in order to meet a specified ...

... (SV = EV - PV). Variance at completion: ...

... What are the processes of cost management? What is the cost management plan and what does it establish? The different ways of estimating costs of a project ...