Project Cost Management Part 2 by Whizlabs Software

video locked

About the Lecture

The lecture Project Cost Management Part 2 by Whizlabs Software is from the course Project Management Professional - Training. It contains the following chapters:

  • Earned value management technique
  • Performance Indexes
  • Example - EVM technique
  • Sample exercise
  • Other concepts

Included Quiz Questions

  1. 1.5
  2. 0.75
  3. 1.33
  4. 0.5
  1. 1.2
  2. 0.83
  3. 0.80
  4. 1.66
  1. 1.0
  2. 0.79
  3. 0.83
  4. Can’t be determined
  1. Parametric Estimating
  2. Expert judgment
  3. Analogous Estimating
  4. Monte-carlo Analysis
  1. 1.0
  2. 0.5
  3. 0,25
  4. 1.25
  1. The project cost expenditures are as per the budget.
  2. The project is on schedule
  3. The project is behind schedule
  4. The project is over budget (cost overrun)
  1. 1.0
  2. 0.67
  3. 1.5
  4. -15 days
  1. The project manager can use the management reserve as and when applicable.
  2. The management reserve accounts for unidentified risk factors.
  3. The management reserve is added on top of the cost baseline.
  4. The management reserve can be a percentage of estimated cost or a fixed amount depending on the nature of the project.
  1. BAC
  2. Cost baseline
  3. Planned time for Completion
  4. AC
  1. 6,000$
  2. 12,000$
  3. 10,000$
  4. 4,000$
  1. -2000$
  2. 2000$
  3. -1000$
  4. 1000$
  1. 85734$
  2. 10000$
  3. 60096$
  4. 30864$
  1. Determine Budgets
  2. Control costs
  3. Estimate Costs
  4. Plan Cost Management
  1. Both a & c
  2. Fixed cost
  3. Indirect cost
  4. Direct cost
  1. Cost estimates of WBS components
  2. Frequency of performing variance analysis
  3. Limit of accuracy for the estimations
  4. Estimating techniques to be used for the project
  1. Determine Budget
  2. Reserve analysis
  3. Estimate Costs
  4. Control Costs
  1. 0.5
  2. 2.0
  3. 0.4
  4. 1.33
  1. 2.0
  2. 0.5
  3. 0.4
  4. 1.33
  1. 1.33
  2. 0.4
  3. 0.5
  4. 2.0
  1. Ball park estimates
  2. Budget estimates
  3. Definitive estimates
  4. Bottom-up estimate

Author of lecture Project Cost Management Part 2

 Whizlabs Software

Whizlabs Software


Customer reviews

(1)
5,0 of 5 stars
5 Stars
5
4 Stars
0
3 Stars
0
2 Stars
0
1  Star
0


Excerpts from the accompanying material

... 7.1 Plan Cost Management: The objective of this process is to create a Cost Management Plan. Cost Management Plan Just like the Scope & Schedule Management Plan, this is also a subset of the Project Management Plan & can be defined as a ...

...with more available information. The primary output of this process is activity cost estimates, which provides the basis of cost estimate. Please note that padding is not an acceptable practice as per PMI. Hence, the cost estimates are kept realistic and as per the calculation. No buffer/tolerance is added to allocate extra cost for the activities being estimated at this point of time. Analogous Estimating: Analogous estimations are done based on historical records. It uses parameters (e.g . scope, cost, ..

...are rolled up to arrive at the project level estimate. More accurate? Gains buy-in from team? Provides a basis for monitoring and control? Takes more time and cost to come up with? Requires the project to be well defined and understood? Three-Point Estimation (PERT): The accuracy of single-point activity estimates can be improved by considering estimation uncertainty and risk. Most likely (M): The estimate of the activity, based on realistic effort assessment for the required work and any predicted expenses Optimistic (O): The activity ...

...packages to establish an authorized cost baseline. The cost baseline includes all authorized budg etc, but excludes management reserves. Reserve Analysis we consider the project buffer with the help of reserve analysis. Budget reserve an analysis can establish both the contingency reserves and the management reserves of the project. Contingency reserve is a separately planned amount used to allow for future situations which may be planned, but only partially. Contingency Reserve Contingency reserves are kept aside, mainly for ...

...for unplanned changes to project scope and cost; say for natural calamity, like: earthquake, flood etc. Project manager does not have access to the management reserve funds without senior management approval; however, contingency reserve is within the reach of the project manager and can be used by the project manager whenever a known risk occur. Bottom- up technique In this example the estimation is being done. Costs of individual activities associated with a work project ...

...the relationship between the consumption of project funds to the physical work being accomplished for such expenditures. Cost control includes: Influencing the factors that create changes to the authorized cost baseline, ...

...used method of performance measurement which integrates project scope, cost, and schedule measures to help the project management team assess and measure project performance and progress. The principles of EVM can be applied to all projects, in any industry. EVM develops and monitors three key dimensions for each work package and control account: Planned Value (PV): It is the authorized budget assigned to the work to be accomplished for an activity or work breakdown structure component.The total of the PV is sometimes referred to as the performance measurement baseline (PMB). The total planned value for the project is ...

...total budget? Estimate at completion (EAC): What you expect the job to cost after some portion of the work has been completed.EAC = BAC / CPI {OR} [ AC / EV ] * BAC? Estimate to Complete (ETC= EAC-AC): How much more do you expect the job to cost after some portion of the work has been completed? Variance at completion (VAC): VAC = BAC-EAC? Percent Completion: EV / BAC Sample exercise? Given the following problem: EV = $55, AC = $67, PV = $56 , BAC = $137? Cost Variance = EV-AC = $55-$67 = -$12, Schedule Variance = EV-PC = $55-$56 = -$1, CPI = EV/AC = 55/67 = .82, SPI = EV/PC = 55/56 = .98, EAC = BAC/CPI = 137/.82 = ...

...of Return: Simple calculation of annual financial return for a given outlay without consideration of any external or related factors. PBP (Payback Period): The number of time periods up to the point at which cumulative revenues exceed cumulative costs and, therefore, the project has turned a profit. BCR (Benefit cost ratio): Benefit-cost ratio (BCR) = PV of revenue/PV of costs. Target Revenue should be at least 1.3 times the cost. Life cycle costing: Evaluatingcost based on the cost of the whole life of the product and not only on ...