About the Lecture

The lecture Define Activities by Sean Whitaker is from the course Archiv - PMP Training – Become a Project Management Professional (EN). It contains the following chapters:

  • Define Activities
  • Tools and Techniques

Included Quiz Questions

  1. The scope baseline is an important input because it contains the WBS and we need to break the WBS work packages down into activities in order to define them.
  2. The scope baseline is an important input because it contains the scope statement and we need to use the scope statement to produce a WBS.
  3. The scope baseline is an important input because it contains the stakeholder register which gives us useful information about stakeholder expectations.
  4. The scope baseline is of no use to us when defining activities.
  1. Rolling wave planning means planning work in the short term in detail and doing less detailed planning for work further away.
  2. Rolling wave planning means redoing faulty work to ensure it is correct.
  3. Rolling wave planning means only planning work the day before it is due to be done.
  4. Rolling wave planning means constantly re-planning work to be done.
  1. Activity list and activity attributes.
  2. Scope statement and milestone list.
  3. WBS and WBS dictionary.
  4. Requirements documentation and requirements tractability matrix.

Author of lecture Define Activities

 Sean Whitaker

Sean Whitaker